Randy,
never received an order from you. As the request was not very high in the past I only had sumps casted for orders placed before. As requests have increased siginificantly I will have a little stock of these sumps from spring on. At the moment I can only confirm what Alex told you. Leadtime for casting is about 6 weeks after order. Machining is another 4-6 weeks. My CNC-suppliers have a lot to do since this year. Economy and especially machine-building has become much better during this year. The result is , that I have leadtimes from up to 8 weeks at the moment, where I had 3 weeks in the last year. Might be so, that I will have my own milling center from next year on. Then everything will become better.
So if you like one, please go the suggested way. Canīt offer you one at the moment. The last batch was sold long before I had them on my workbench.
Martin
|